Construction continues on Green River roads

Residents will continue to have road construction to drive around, at least until the end of September.

A state-funded project focusing on Hitching Post Drive, West Teton Boulevard and East Teton Boulevard is underway while a sixth-penny funded city project continues along Second South Street. City Utility Manager Mark Westenskow said he hopes most of the work on Hitching Post Drive will conclude by the time school starts, but admits he doesn’t have too much control over the timeline as it is a state project. Work on Second South should wrap up by the end of September he said, with paving completed.

He said some clean up work will take place during the early spring months, but said it’s easier to finish paving before the winter months and take on clean up once spring starts.

Improvements being made to Second South Street totals $4,666,095, with work including the installation of a new water main, as well as reconstruction of the street, gutter and sidewalk.

 

Reader Comments(0)